Mechanical Fixing of Rhepanol: Systems and Design
Mechanically fixed Rhepanol hfk is secured to the deck through a specified attachment system. Screw counts are not a universal preset: roof zones, deck, fastener capacity and wind-uplift loads determine the layout.
ROOF MEMBRANES · RHEPANOL (PIB)
Mechanically fixed Rhepanol hfk is secured to the deck through a specified attachment system. Screw counts are not a universal preset: roof zones, deck, fastener capacity and wind-uplift loads determine the layout.
FDT documents mechanical hfk roof assemblies, including fastening within the lap. Use the specified fasteners, weldable seam zone and project-specific fixing plan. A generic screws-per-square-metre allowance is not a substitute for wind design.
What mechanical fixing of hfk means
FDT describes attachment at the membrane overlap within certain mechanically fixed hfk assemblies. The sheet is positioned and secured, with the seam closed using the specified hot-air weld.
Other application concepts exist; do not apply one mechanical detail to every Rhepanol type. Start with the exact hfk product.
Deck, insulation and wind zones
Identify steel, timber, concrete or other deck, the insulation and intervening layers. Fastener pull-out resistance and compatibility depend on the actual substrate.
Corners, perimeters and field areas may have different wind loads. A project-specific layout is needed; see roof safety and wind uplift.
Never use a generic five screws per m² as a definitive Rhepanol fixing specification.
Lap placement and seam design
Mechanically attached membranes require correct laps and adequate clean weldable seam width. FDT sets requirements for fastening positions, overlaps and system geometry; use the latest manual for the exact variant.
Compatible seam zones are hot-air welded and inspected. See welding and inspection rather than copying a PVC fixing or weld detail.
Estimate material without pretending to design
An estimator can record roof area, perimeters and suitable fixing types, but the final fastener count belongs to the calculated wind and fixing schedule.
Separate fasteners, plates, seam work, labour and any additional profiles in the material schedule and the cost breakdown.
A 60 m² roof does not yield a valid screw count without wind zones and deck data. Enter the actual count after the approved fixing plan.
Pre-work checks
Check the approved FDT system, substrate strength, insulation fixing, edge distances, wind plan, penetrations and weld inspection access.
Record any departures from specification. A quotation saying mechanically fastened is not a structural design. Some assemblies may instead use partial bonding or ballast.
Estimate Rhepanol roof area, rolls and materials
Select PIB (Rhepanol), verify the hfk roll format and enter actual supplier purchase prices. DakCalc provides a provisional material estimate, not an approved laying plan, wind design or FDT system certification. Verify the delivered hg roll format and configuration.
Open the DakCalc calculator →More Rhepanol guides
Also useful in the knowledge hub: roofing system comparison, calculating membrane laps, roof-edge trims and corners.
Frequently asked questions
How many screws per m² for Rhepanol?
There is no universal safe quantity. Use a project wind-uplift calculation and approved FDT fixing schedule.
Are mechanically fastened hfk seams welded?
Yes, FDT documents hot-air welded hfk membrane joints in these assemblies.
Can generic PVC fasteners be substituted?
Only if documented as compatible within the selected PIB roof system; never assume they are interchangeable.